Thursday, April 30, 2009

More wine storage - back bar


We've installed the distressed mirror behind the bar and constructed a cabinet to hold our valuable wines. Next step - paint, handles and hinges.

Wednesday, April 29, 2009

Passed the Electrical Inspection

Electrical Inspector signed off on everything. So far, so good! Now if the plumber would just show up to finish his work!

Monday, April 27, 2009

Final Electrical Inspection

Scheduled for Tuesday!

Waiting on plumbing, fire and health inspections.

Sunday, April 26, 2009

Friday, April 24, 2009

Wine Storage


Construction of wine storage units.

Clean Hood


Hood cleaning company came in and completed a top-to-bottom scrubbing of the hood system.

Patio Pavers - Day 2

Wednesday, April 22, 2009

Sunday, April 19, 2009

Saturday, April 18, 2009

Paint - Outside (and patio pavers)


Window surround - painted black.
Patio pavers - ready for installation.
(A next step - new shingles for roof of bay windows.)

Paint - Outside


Black around the windows.

Friday, April 17, 2009

Hand Sink in Kitchen

3 Compartment Sink


Installed!

Plumber returns - Hot Water Heater and Mop Sink


The plumber has returned to the scene of the crime and is installing fixtures.

Monday, April 13, 2009

Painting Outside




Window surrounds are primed.

Sunday, April 12, 2009

Saturday, April 11, 2009

Thursday, April 9, 2009

More pine tile pics


Wood Flooring - pine tiles


We've borrowed the idea for end grain flooring and are using old pine 2x6s from Community Forklift and slicing them into 3/4" pieces. Then we turned them on their side and glued them to the floor.

Wednesday, April 8, 2009

Bench in West Bay Window


Construction begins.

Tuesday, April 7, 2009

SubFloor


SubFloor installed in the bay window on 11th Street. Next step - hardwood end grain flooring.

New Fence


Both iron fence and wood fence are up. Next step - 3 new gates.

Monday, April 6, 2009

Room 11 Email List

If you want to be on our email list, send me an email -
paul (at) room11dc.com

We'll be sending out deets about opening dates, construction progress, ideas for the food and drinx menu, etc.

Harry Painting in the Windows

Sunday, April 5, 2009

Painting - Continues


Keep on moving!

Paint - In progress


First the primer, then the finish coat.

Saturday, April 4, 2009

Finished Drywall


Ready for Paint!

Friday, April 3, 2009

New Bathroom Door


Waiting for hardware.

Bar Floor - Tile is complete


Next step is the grout!

Bar Floor - Halfway


50% finished!

Thursday, April 2, 2009

Wednesday, April 1, 2009